Final answer:
The correct sequence of steps in the control process is c) Step 1, Step 2, Step 3, Step 4, which includes setting performance levels, measuring actual performance, comparing it to standards, and taking corrective action.
Step-by-step explanation:
The correct sequence of steps in the control process is established as Step 1-The desired performance level for a given goal, followed by Step 2-Measured actual performance, then Step 3-Comparing measured performance to established standards, and finally Step 4-Applying corrective action if necessary. The correct answer is c) Step 1, Step 2, Step 3, Step 4. This sequence ensures that organizational goals are met effectively by first setting a benchmark, then measuring performance against this benchmark, analyzing any disparities, and then making adjustments to align actual performance with the desired performance level.