Final answer:
The cycle time required to meet the current demand of 92 burritos per hour is 39.13 seconds per burrito, corresponding to option E.
Step-by-step explanation:
The student has asked about calculating the cycle time to meet a specific demand for burritos, which involves a mathematical operation within the scope of business operations. The formula to compute the takt time is given as Operating Time divided by Demand. To meet the current demand of 92 burritos per hour, and assuming that the operating time is one hour (or 3600 seconds), we need to divide the operating time by the demand:
Operating Time (in seconds) / Demand (burritos per hour) = Takt Time (in seconds per burrito)
3600 seconds / 92 burritos = 39.13 seconds per burrito
Therefore, the cycle time required to meet the current demand of 92 burritos per hour is 39.13 seconds per burrito, which corresponds to option E.