What is the Product Owner accountable for in Scrum?(choose the best answer)

A. Writing the User Stories so they are comprehensive enough for the stakeholders.
B. Maximizing the value of the product resulting from the work of the Scrum Team.
C. Refining the top level Product Backlog items until they are ready to be handed over to the Scrum Team.
D. Describing an Increment at Sprint Planning and making sure that the Developers deliver it by the end of the Sprint.

1 Answer

3 votes

Final answer:

The Product Owner in Scrum is accountable for maximizing the value of the product resulting from the work of the Scrum Team.

Step-by-step explanation:

The Product Owner in Scrum is accountable for maximizing the value of the product resulting from the work of the Scrum Team. This involves creating and prioritizing the Product Backlog, which is a list of features, enhancements, and fixes that the team will work on. The Product Owner is responsible for understanding the needs of the stakeholders and ensuring that the team is delivering a product that meets those needs.

The Product Owner is not accountable for writing the User Stories, as this is a collaborative effort between the Product Owner and the development team. The Product Owner does not refine the top-level Product Backlog items until they are ready to be handed over to the team, as backlog refinement is a continuous process. Finally, describing an Increment at Sprint Planning and ensuring its delivery is the responsibility of the entire Scrum Team, not just the Product Owner.