Final answer:
The collaborative event in Scrum where the team plans the current sprint's work is called Sprint Planning. It involves selecting tasks from the product backlog and creating a sprint backlog with detailed deliverables. The correct option is d.
Step-by-step explanation:
The term for the collaborative event in Scrum in which the Scrum team plans the work for the current sprint is Sprint Planning.
During Sprint Planning, the team selects items from the product backlog that they can commit to completing during the sprint. This meeting is an opportunity to agree on a sprint goal and discuss the details of the work required.
The outcome is a sprint backlog that details the tasks and user stories the team will deliver by the end of the sprint. The correct option is d.