Final answer:
The military validates MILCON projects at three different levels: SRM, MINCON, and MAJCON.
Step-by-step explanation:
In the military, each MILCON project is validated at different levels depending on its size, cost, and scope. The three levels of validation are:
- Sustainment, Restoration, and Modernization (SRM): This level validates projects with a small scope or limited cost and focuses on maintaining and improving existing military facilities.
- Minor Construction (MINCON): This level validates projects with a moderate scope and cost, such as constructing new buildings or making significant renovations.
- Major Construction (MAJCON): This level validates large-scale and high-cost projects, such as building new bases or significant infrastructure.
Each level of validation requires a different approval process and level of scrutiny to ensure that the MILCON project aligns with the military's strategic goals and priorities.