Requirements are missed during elicitation that does not relate the software projects shooklril be finished on time

A False
B True

1 Answer

4 votes

Final answer:

Requirements missed during elicitation can impact the timely completion of software projects.

Step-by-step explanation:

The statement is true. When requirements are missed during the elicitation process of a software project, it can lead to delays and difficulties in finishing the project on time. Elicitation involves gathering and understanding the needs and expectations of the stakeholders. If important requirements are not properly identified and documented during this phase, it can result in misunderstandings, scope changes, and rework later in the development process, which can impact the project schedule.