Answer:
Jefferson Company
1. An example of a direct cost is the cost of direct raw materials. An example of an overhead cost is cost of factory repairs and maintenance.
2. The overhead allocated to Job A21 as of February 1 is $40,000.
3. The overhead allocated to Job A24 as of February 28 is $32.000.
4. The under-allocated overhead for February is $6,000
5. The ending balance of jobs still in process as of February 28 is $92,000.
6. The Cost of Jobs Billed for February is $394,000.
Step-by-step explanation:
a) Data and Calculations:
Budgeted overhead allocation rate = 80% of direct labor costs
Beginning WIP:
Materials $30,000
Direct labor 50,000
Overhead 40,000 ($50,000 * 80%)
Overhead allocated to Job A21 as of February 1 = $40,000 ($50,000 * 80%)
Overhead allocated to Job A24 as of February 28 = $32,000 ($40,000 * 80%)
Total overhead allocated for February = $96,000 ($120,000 * 80%)
Actual overhead costs incurred = $102,000
Therefore, the under-allocated overhead for February = $6,000
The ending balance of jobs still in process as of February 28 (Job A24) =
Materials costs = $20,000
Labor costs = $40,000
Overhead applied = $32,000
Total costs = $92,000
Cost of Jobs Billed:
Beginning WIP: Cost of Job A21 = $120,000 ($30,000 + 50,000 + 40,000)
Costs incurred during the period:
Cost of Direct Materials 150,000
Cost of Direct Labor 120,000
Allocated overhead costs 96,000
Total costs of production = $486,000
Less Ending WIP (Job A24) = 92,000
Cost of Jobs Billed for February $394,000