A first-class engineer may take charge of a boiler plant not to exceed:

a) 150 horsepower
b) 600 horsepower
c) 500 horsepower

1 Answer

4 votes

Final answer:

b) 600 horsepower. A first-class engineer may take charge of a boiler plant not to exceed 600 horsepower.

Step-by-step explanation:

A first-class engineer may take charge of a boiler plant not to exceed 600 horsepower.