Final answer:
To find the EV (Earned Value or Budgeted Cost of Work Performed), you need to calculate the percentage of completed work and multiply it by the BAC (Budget at Completion). In this case, the EV is $333,333.33.
Step-by-step explanation:
To find the EV (Earned Value or Budgeted Cost of Work Performed), you need to calculate the percentage of completed work and multiply it by the BAC (Budget at Completion).
Percentage of completed work = Number of completed features / Total number of features
In this case, we have completed 2 features out of 6, so the percentage of completed work is 2 / 6 = 0.3333
EV = 0.3333 x 1,000,000 = $333,333.33