Final answer:
The outputs of the sprint planning meeting include the sprint backlog, groomed product backlog, and refined sprint goal.
Step-by-step explanation:
The outputs of the sprint planning meeting include:
- Sprint backlog: This is a list of tasks that the development team plans to complete during the upcoming sprint.
- Groomed product backlog: This is an updated version of the product backlog that has been refined and prioritized.
- Refined sprint goal: This is a clear and concise statement that describes what the development team aims to accomplish during the sprint.
Team capacity, however, is not an output of the sprint planning meeting. It refers to the available resources and skills of the development team.