At what levels does risk management take place in Scrum? Select all that apply.

a) Project level
b) Personal level
c) Team level
d) Sprint level

1 Answer

4 votes

Final answer:

In Scrum, risk management occurs at the project level, team level, and sprint level, addressing risks that could impact the overall project, team dynamics, and sprint goals respectively.

Step-by-step explanation:

Risk management within the context of Scrum can take place at multiple levels. These levels include:

  • Project level: This encompasses risks that affect the overall project including scope, timelines, and resources.
  • Team level: Risks are managed by the Scrum team, which can comprise developers, a Scrum Master, and Product Owner, addressing issues such as team dynamics and skill levels.
  • Sprint level: In each sprint, which is a set period during which specific work must be completed and made ready for review, the team identifies and manages risks related to the sprint goal.
  • As for the Personal level, it is not typically a focus of risk management within the Scrum framework. Instead, risks are managed collaboratively by the team as a whole.

Therefore, the correct answers are a) Project level, c) Team level, and d) Sprint level.