Final answer:
To calculate Earned Value (EV) for a project at the end of month 6 with a BAC of $100,000, one must determine the percentage of project completion. Multiply the completion percentage by the BAC to find the EV. However, additional project-specific details are required for an accurate EV calculation.
Step-by-step explanation:
The calculation of Earned Value (EV) at the end of month 6 for a project with a Budget at Completion (BAC) of $100,000 typically involves assessing the work performed and the costs incurred up to that point in time. EV is a key component of Earned Value Management (EVM), a project management technique used to measure project performance and progress in an objective manner. However, the information provided in the question does not clearly state the actual works performed or the planned value (PV) which is necessary to compute EV. Typically, EV is calculated by multiplying the percent complete of the project work with the BAC. For example, if the project is exactly 50% complete, the EV would be 0.50 x $100,000 = $50,000.
It is important to note that the references about the EBM, Yelberton's rate of return, and the total cost of buying the basket in the question seem unrelated to the fundamental concept of Earned Value and the direct calculation of EV from BAC for a project management context.