Iterative project life cycles are sequenced into a set of distinct phases, from the development of the initial concept to the deployment of an ultimate outcome, output or benefits. This approach aims to be highly structured, predictable and stable. Select one:

A. True
B. False

User Ventaur
by
7.8k points

1 Answer

4 votes

Final answer:

The statement False is the correct answer. Iterative project life cycles involve repetitive cycles where designs are developed, prototyped, evaluated, and changes are made based on the improved understanding.

Step-by-step explanation:

The statement False is the correct answer. Iterative project life cycles are not highly structured and predictable. Instead, they involve repetitive cycles where designs are developed, prototyped, evaluated, and changes are made based on the improved understanding.