227k views
0 votes
You are managing the construction of a new expert. The project is scheduled to be completed in 2 years with an approved budget of 30,000,000QR. At the end of the first year, the value of the work completed to 18,000,000QR. The actual costs are 14,400,000.Find BAC,PVI,EV,AC,SV,CV,SPI,CPI,EAC,TCPI

User Lukastymo
by
8.4k points

1 Answer

3 votes

Final answer:

The BAC is 30,000,000QR, PVI is 30,000,000QR, EV is 18,000,000QR, AC is 14,400,000QR, SV is -12,000,000QR, CV is 3,600,000QR, SPI is 0.6, CPI is 1.25, EAC is 24,000,000QR, and TCPI is 1.67.

Step-by-step explanation:

BAC (Budget at Completion): BAC = 30,000,000QR as it is the approved budget for the project.

PVI (Planned Value of the work): PVI = 30,000,000QR as it is the approved budget for the entire project.

EV (Earned Value): EV = 18,000,000QR as this is the value of the work completed at the end of the first year.

AC (Actual Cost): AC = 14,400,000QR as this is the actual cost incurred at the end of the first year.

SV (Schedule Variance): SV = EV - PVI = 18,000,000QR - 30,000,000QR = -12,000,000QR.

CV (Cost Variance): CV = EV - AC = 18,000,000QR - 14,400,000QR = 3,600,000QR.

SPI (Schedule Performance Index): SPI = EV / PVI = 18,000,000QR / 30,000,000QR = 0.6 (or 60%).

CPI (Cost Performance Index): CPI = EV / AC = 18,000,000QR / 14,400,000QR = 1.25.

EAC (Estimate at Completion): EAC = BAC / CPI = 30,000,000QR / 1.25 = 24,000,000QR.

TCPI (To-Complete Performance Index): TCPI = (BAC - EV) / (BAC - AC) = (30,000,000QR - 18,000,000QR) / (30,000,000QR - 14,400,000QR) = 1.67.

User Zvezdochka
by
8.4k points

No related questions found