Final answer:
The average completion time for the value-added process is 9.9 hours. The standard deviation for the entire process is 9.01 hours. The probability of completing the process in certain timeframes can be calculated using the mean and standard deviation. A 95 percent confidence interval for the process can be developed using the formula.
Step-by-step explanation:
To calculate the average completion time for the value-added process, we can sum up the times for each activity and divide by the total number of activities. In this case, the sum of the times is 8 + 15 + 10 + 10 + 8 + 15 + 6 + 20 + 3 + 4 = 99 hours. Since there are 10 activities, the average completion time is 99/10 = 9.9 hours.
To calculate the standard deviation for the entire process, we can use the formula for population standard deviation. First, we calculate the squared difference between each activity time and the average completion time: (8-9.9)^2 + (15-9.9)^2 + (10-9.9)^2 + (10-9.9)^2 + (8-9.9)^2 + (15-9.9)^2 + (6-9.9)^2 + (20-9.9)^2 + (3-9.9)^2 + (4-9.9)^2 = 810.74. Then, we divide this value by the total number of activities, which is 10, and take the square root: sqrt(810.74/10) ≈ 9.01 hours.
To calculate the probability that the process will be completed in a certain amount of time, we can assume that the completion times follow a normal distribution. We can then use the mean and standard deviation calculated previously to calculate the z-score for each target time and look up the corresponding probability in the standard normal distribution table. For example, to calculate the probability that the process will be completed in 75 hours, we calculate the z-score using the formula z = (75 - 9.9) / 9.01 ≈ 8.04. Looking up this z-score in the table, we find that the probability is extremely close to 1. Similarly, we can calculate the probabilities for 80 hours and 70 hours.
To develop a 95 percent confidence interval for the process, we can use the formula: CI = mean ± (1.96 * (standard deviation / sqrt(n))), where n is the number of activities. In this case, the mean is 9.9 hours, the standard deviation is 9.01 hours, and n is 10. Plugging in these values, we get: CI = 9.9 ± (1.96 * (9.01 / sqrt(10))). Calculating this, we find that the confidence interval is approximately 5.78 to 14.02 hours.
If you aren't confident in your ability to make delivery promises, it would be best to target your improvement efforts towards reducing the variability in the completion times of each activity. By minimizing the standard deviation, you can increase the predictability and reliability of your delivery estimates.
To proceed, you can analyze the specific activities with higher variability and identify the root causes of the variability. You may consider implementing process improvements, such as standardizing procedures, training employees, or implementing quality control measures, to reduce the variability and improve the overall efficiency of the value-added process.