Final Answer:
The Overall Equipment Effectiveness (OEE) of the copy machine is 73.6%, reflecting its efficiency. This calculation considers Availability (25.6%), Performance (50%), and Quality (80%) factors in the production process. The OEE is the product of these three components.
Step-by-step explanation:
The Overall Equipment Effectiveness (OEE) is a key performance indicator that measures the efficiency of a manufacturing process. It is calculated by multiplying three factors: Availability, Performance, and Quality.
1. Availability (A): This represents the machine's uptime. In this case, the machine is available 24 hours a day, producing 92 jobs. The total available time is given by 24 hours 60 minutes = 1440 minutes. The actual production time is the total number of jobs multiplied by the processing time per job, which is 92 jobs * 4 minutes/job = 368 minutes. Therefore, Availability (A) is calculated as

2. Performance (P): This factor considers the speed at which the machine operates compared to its maximum capability. The setup time and processing time for a job are both 4 minutes, but only 2 minutes of processing time contribute to production. Therefore, Performance (P) is

3. Quality (Q): Quality accounts for the rework factor. Since 20% of the jobs require rework, the Quality (Q) is

Now, the OEE is calculated by multiplying these three factors:
Therefore, the Overall Equipment Effectiveness of the copy machine is 73.6%.