Final answer:
The aspects of project change control documented in a communication plan include how stakeholders will be notified of changes and how the evaluation/decision-making process occurs.
option a is the correct
Step-by-step explanation:
The aspects of project change control that are documented within a communication plan at the start of a project include:
- How stakeholders will be notified of changes:
- This includes the methods and channels of communication that will be used to inform stakeholders about any changes in the project.
- How the evaluation/decision-making process occurs:
- This involves documenting the steps involved in evaluating changes, making decisions, and implementing them.