Final answer:
The correct answer is option 3. Tracie Corporation's direct labor cost for September is found by calculating the total labor hours required for that month's production and multiplying by the hourly labor cost, resulting in $213,120.
Step-by-step explanation:
The question asks to calculate Tracie Corporation's direct labor cost for the month of September. To find the total labor cost, we need to multiply the number of labor hours required for September's budgeted production by the average hourly cost of direct labor. Each unit requires 0.8 hours of labor and the hourly cost is $18.
First, calculate the total labor hours needed for production: 14,800 units × 0.8 hours/unit = 11,840 hours. Then, calculate the total cost: 11,840 hours × $18/hour = $213,120. This is the direct labor cost for September.