What does WBS stand for in project management?

a) Work Breakdown Structure
b) Work-Based Schedule
c) Work Budgeting System
d) Workload Breakdown Schedule

User Zeograd
by
8.2k points

1 Answer

6 votes

Final answer:

A Work Breakdown Structure (WBS) is a hierarchical representation of the tasks and deliverables required to complete a project.

Step-by-step explanation:

The correct answer is a) Work Breakdown Structure.

A Work Breakdown Structure (WBS) is a hierarchical representation of the tasks and deliverables required to complete a project. It breaks down the project into smaller, manageable components, allowing the project team to effectively plan, execute, and control the project.

For example, in a construction project, the WBS may include tasks such as site preparation, foundation construction, framing, electrical installation, and plumbing installation. Each task can be further broken down into subtasks, creating a structured roadmap of the entire project.