Which of the following components is typically part of a Schedule Management Plan for a project?

A) Project risk assessment
B) Cost control procedures
C) Activity duration estimates
D) Marketing strategies

User Sathiyan S
by
9.3k points

1 Answer

3 votes

Final answer:

Activity duration estimates is typically part of a Schedule Management Plan for a project.

Step-by-step explanation:

The component typically part of a Schedule Management Plan for a project is Activity duration estimates. This component involves determining the amount of time required to complete each activity in the project schedule. By estimating activity durations accurately, project managers can create realistic and achievable project schedules.