What relationship between work packages and the work breakdown structure (wbs) does the time phased work package budget demonstrate? multiple choice question.

O all work packages are built on a five week horizon.
O more than one work package can be represented by a wbs activity.
O work packages only include labor costs, and baseline budgets are only for labor.

1 Answer

0 votes

Final answer:

The time-phased work package budget demonstrates the distribution of project costs over time and shows that more than one work package can be represented by a single WBS activity. This reflects the structure of a WBS where smaller work packages that include various cost types are organized under broader project activities. So, the correct option is O more than one work package can be represented by a wbs activity.

Step-by-step explanation:

Relationship Between Work Packages and WBS

The question pertains to the area of project management, and specifically to the process of developing a Work Breakdown Structure (WBS) and defining work packages within it. The time-phased work package budget shows the cost estimates for the completion of work packages which are components of the WBS over a certain period. It represents how the cumulative costs are distributed over the project timeline, and typically includes various cost types such as labor, materials, and overheads.

Now, to address the multiple-choice question: the correct option is that more than one work package can be represented by a WBS activity. This reflects the hierarchical nature of a WBS where larger activities are broken down into smaller, more manageable packages of work that can be scheduled, budgeted, and monitored independently. Contrary to the other options, a WBS is not necessarily built on a fixed time horizon like five weeks, and work packages include not only labor costs but can also incorporate material, equipment, and other direct and indirect costs.

Understanding the relationship between work packages and the WBS is crucial for project managers to effectively plan, execute, and control project costs. The WBS is the backbone of the project that defines the total scope into manageable chunks, whilst work packages are the building blocks that detail the work involved along with their respective budgets. In summary, each work package details the work, resources, and budget necessary to complete a portion of the project and collectively, they roll up to create the comprehensive WBS which outlines the entire project scope.