Suppose task c has two predecessor tasks: task a and task b. task a ends on may 8 and task b ends on may 13. when can task c begin?

a. may 12
b. may 8
c. may 10
d. may 14

User Saranicole
by
7.9k points

1 Answer

5 votes

Final answer:

Tje correct answer is option d. Task C cannot begin until both of its predecessor tasks, Task A and Task B, have been completed. Since Task B finishes on May 13, the earliest Task C can begin is May 14.

Step-by-step explanation:

The student's question concerns the scheduling aspect of project management, which is a key concept in business studies. In the given scenario, Task C has two predecessor tasks: Task A, which ends on May 8, and Task B, which ends on May 13. As per the rules of project scheduling, a succeeding task cannot begin until all of its predecessor tasks have completed.



Therefore, Task C can only begin after both Task A and Task B have finished. Since Task B is the last to end on May 13, Task C can commence on the next day after Task B completes. Thus, the correct option for when Task C can begin would be the day following the completion of Task B.



In project management and scheduling, it's imperative to identify the latest ending date of all predecessor tasks to determine the earliest start date for a subsequent task. If we apply this logic to the current question, the earliest start date for Task C is the day after May 13, which is May 14, aligning with option d. Hence, the correct answer to the question is option d. May 14.