you have been given a task which might take 60 days to complete; however if the conditions are favorable it might be completed in 55 days. in the worst case scenario, it may take 70 days. find the average estimate for this task using triangular estimate.

User Pydsigner
by
8.0k points

1 Answer

1 vote

Final answer:

The average estimate for completing the task using the triangular estimate is approximately 59.17 days.

Step-by-step explanation:

The triangular estimate is a technique used to find the average estimate for a task with different completion times. To find the average estimate, we take the weighted average of the best case, worst case, and most likely case scenarios. In this case, the best case scenario is 55 days, the worst case scenario is 70 days, and the most likely case is 60 days.

To calculate the average estimate, we use the formula:

Average Estimate = (Best Case + 4 x Most Likely Case + Worst Case) / 6

Substituting in the values:

Average Estimate = (55 + 4 x 60 + 70) / 6 = 59.17 days

So, the average estimate for completing the task using the triangular estimate is approximately 59.17 days.