As a project is crashed and project duration is reduced, indirect costs typically group of answer choices

a. become unstable.
b. increase.
c. decrease.
d. stay the same.
e. become unreliable.

User Eoldre
by
8.5k points

1 Answer

6 votes

Final answer:

Indirect costs typically increase when a project is crashed because more resources are consumed in a shorter timeframe to accelerate the project, which raises expenses like administrative and facility costs.B is the correct option.

Step-by-step explanation:

When a project is crashed and the project duration is reduced, indirect costs typically increase.

This happens because while the project duration is reduced, more resources are usually needed in a shorter period of time, leading to an increase in costs such as overtime pay, additional staffing, or expedited shipping fees for materials. Indirect costs are those expenses that are not directly related to the specific activities in the project, such as administrative costs, facility costs, or utilities, which tend to rise as the intensity and pace of work are accelerated.

The mentioned correct option for what happens to the indirect costs when a project is crashed is option b. increase.