Final answer:
The schedule performance index (SPI) is 0.8 and the cost performance index (CPI) is 0.7.
Step-by-step explanation:
The schedule performance index (SPI) measures the efficiency or progress of a project in relation to its planned schedule. It is calculated by dividing the actual percent complete (80% in this case) by the planned percent complete (100%). In this case, the SPI is 0.8, indicating that the project is running behind schedule.
The cost performance index (CPI) measures the efficiency or progress of a project in relation to its planned cost. It is calculated by dividing the earned value (actual cost) by the planned value (budget). In this case, the CPI is 0.7 (7K/10K), indicating that the project is over budget.