Final answer:
The z-value for the probability of completing the project before 26 weeks, with an expected completion time of 36 weeks and a variance of 7 weeks, is approximately -3.774.
Step-by-step explanation:
To calculate the z-value for the probability of completing the project before 26 weeks when the mean completion time is 36 weeks and the variance is 7 weeks, we first need to find the standard deviation. The variance is the square of the standard deviation, so the standard deviation (σ) is the square root of the variance, which is √7 ≈ 2.646 weeks.
The z-value is then calculated using the formula: z = (X - μ) / σ, where X is the time we are interested in (26 weeks), μ is the mean (36 weeks), and σ is the standard deviation. Plugging the numbers into the formula gives us: z = (26 - 36) / 2.646, which results in z ≈ -3.774.