Final answer:
The project budget can be calculated by summing the cost baseline ($200,000), the contingency reserve ($40,000), and the management reserve which is 6% of the cost baseline ($12,000). This results in a total project budget of $252,000.
Step-by-step explanation:
To calculate the project budget, we start with the sum of all work packages which amounts to $200,000. This is known as the cost baseline. Next, we add the estimated contingency reserve of $40,000. Then we must consider the management reserve, which is calculated as 6% of the cost baseline. Therefore, 6% of the cost baseline ($200,000) is $12,000.
Adding all these figures together, the project budget can be determined as follows:
Project Budget = Cost Baseline + Contingency Reserve + Management Reserve
Project Budget = $200,000 + $40,000 + $12,000
Project Budget = $252,000
The total project budget is therefore calculated to be $252,000.