Final answer:
Joe, the project PM, is in the Initiate stage of the project life cycle.
Step-by-step explanation:
Joe, the project PM, is in the Initiate stage of the project life cycle.
In the project life cycle, the Initiate stage is the first phase where the project is identified, defined, and a project charter is developed.
Joe has just finished the project charter, which is a document that formally authorizes the project and provides a high-level overview of its objectives, scope, and stakeholders. This indicates that Joe is in the Initiate stage of the project life cycle.