During the executing process, a project manager has been asked to create an issue log. Which of the following components are included in an issue log?

Each correct answer represents a complete solution. Choose all that apply.
A. The date the issue was submitted
B. The description of the issue
C. The risk register
D. The resource breakdown structure

User Erikk Ross
by
8.5k points

1 Answer

5 votes

Final answer:

An issue log typically includes the date the issue was submitted and the description of the issue, but does not include the risk register or the resource breakdown structure.

Step-by-step explanation:

During the execution process of a project, a project manager should include specific components in an issue log. Key components of an issue log are A) The date the issue was submitted and B) The description of the issue. These elements are important as they help to track when the issue arose and give clarity on what the issue is. It's important to note that C) The risk register and D) The resource breakdown structure are not typically parts of an issue log but are separate documents used in project management. The risk register is used to document potential risks and their management strategies, while the resource breakdown structure is a tool to visually display all the resources required for a project, categorized by type.