Answer:
$180
Step-by-step explanation:
Calculation for What are the total overhead costs assigned to Job 101
Using this formula
Total overhead costs assigned to Job 101=(Total Overhead/Total Machine-hours)*Machine-hours
Let plug in the formula
Total overhead costs assigned to Job 101 = ($90,000/10,000) *20
Total overhead costs assigned to Job 101=9*20
Total overhead costs assigned to Job 101=$180
Therefore Total overhead costs assigned to Job 101 will be $180