The lowest level of the Risk Breakdown Structure(RBS) can be used as a starting point for a checklist.

A. True
B. False

1 Answer

1 vote

Final answer:

The statement is true; the lowest level of the RBS is detailed and specific, making it suitable for creating a risk management checklist. Option A

Step-by-step explanation:

The statement that 'the lowest level of the Risk Breakdown Structure (RBS) can be used as a starting point for a checklist' is True. The Risk Breakdown Structure is a tool used in project management to categorize project risks. It is structured much like the Work Breakdown Structure (WBS) but is focused on identifying potential risks instead of tasks.

The lowest level, often referred to as the work package level in WBS, is detailed and specific in the case of RBS, which makes it useful for the development of a checklist for risk identification and management. Each item at this level can be considered for its likelihood of occurrence and potential impact, allowing for a comprehensive approach to anticipating and mitigating project risks. Option A

User Patrick Hurst
by
8.2k points