86.7k views
1 vote
Which of the following conditions indicate that a process step is a constraint in a sequential process flow where customer demand is not being met?

A) Throughput for the process step is higher than any other process step
B) The process step requires more operators than any other process step
C) Cycle time for the process step is longer than any other process step
D) The process step requires more setup time than any other process step
E) Work-in-process for the process step is lower than any other process step

1 Answer

4 votes

Final answer:

The correct answer is option C, cycle time for the process step being longer than any other process step, as it indicates a bottleneck that could constrain the entire process and hinder the ability to meet customer demand.

Step-by-step explanation:

To determine which conditions indicate that a process step is a constraint in a sequential process flow where customer demand is not being met, let's examine the options provided. A constraint in a production process is a step that limits the throughput of the entire system, reducing its capacity to meet customer demand.

Out of the options:

  • Option A is incorrect because if throughput for the process step is higher than any other process step, it is likely not the constraint but rather a step that is functioning efficiently.
  • Option B is an operational concern and may suggest inefficiency, but more operators do not inherently indicate a process step is a constraint.
  • Option C is correct because if the cycle time for the process step is longer than any other process step, it can slow down the entire process flow, thus creating a bottleneck and becoming a constraint.
  • Option D, like option B, might suggest inefficiency, but more setup time alone does not necessarily make the step a constraint unless it directly affects the flow of the entire process.
  • Option E does not indicate a constraint as having lower work-in-process typically suggests a step that is not a bottleneck.

So, the correct answer is option C, where the cycle time for the process step is longer than any other process step.

User Vijay Hulmani
by
7.3k points