What are Accepted deliverables, Work performance information, Change requests, and project documents updates?

User Imjaydeep
by
7.3k points

1 Answer

2 votes

Final answer:

Accepted deliverables, Work performance information, Change requests, and project documents updates are all part of project management and are related to managing and monitoring the progress of a project.

Step-by-step explanation:

Accepted deliverables, Work performance information, Change requests, and project documents updates are all part of project management and are related to managing and monitoring the progress of a project.

Accepted deliverables refer to the completed and approved work packages or deliverables that meet the project requirements and have been verified by the project stakeholders.

Work performance information includes data and reports on how the project is progressing, such as actual versus planned performance, schedule and cost variances, and any issues or risks identified.

Change requests are formal requests to modify project scope, schedule, budget, or resources due to changes in project requirements, constraints, or risks.

Project documents updates involve revising and updating project-related documents, such as the project management plan, risk register, and communication plan, to reflect changes and progress in the project.