96 men can complete a work in 10 days. they start the work and after 2 days 2 men leave. in how many days will the work be completed by the remaining men?

User Buras
by
7.7k points

1 Answer

6 votes
Total work = 960

Work done in 2 days = 192

Work left = 960 - 192 = 768

Now 94 men complete the 768 work = 768/94 Answer