If a can complete a work in 12 days, b in 15 days and c can do the same work in 20 days. a started the work and left after 2 day the remaining work by b in how many days?

a. 25
b. 33
c. 25/2
d. none

1 Answer

1 vote

Final answer:

B would take 25/2 days to complete the remaining work.

Step-by-step explanation:

To find out how many days it would take for B to complete the remaining work after A left, we need to determine how much work A has done in the 2 days. Since A can complete the work in 12 days, he completes 1/12th of the work in one day. Therefore, in 2 days, A completes 1/12 x 2 = 1/6th of the work. The remaining work is (1 - 1/6 = 5/6) of the total work. Since B can complete the work in 15 days, he completes 1/15th of the work in one day. Therefore, it would take B 15 x (5/6) = 25/2 days to complete the remaining work. So the answer is c. 25/2 days.

User Nellius
by
7.1k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories