Final answer:
Reilly Ltd should undertake the special job as the total relevant costs of £84,600 are less than the revenue of £88,000, resulting in a profit of £3,400.
Step-by-step explanation:
To decide whether or not Reilly Ltd should undertake the special job with a customer willing to pay £88,000, we must calculate the relevant costs. Only costs that will be directly impacted by the decision should be considered, meaning costs that will occur if and only if the project is accepted. Such costs are sometimes called incremental costs or differential costs and do not include sunk costs or costs that will remain the same whether the project is undertaken or not.
Material A requires 2,000 units with none in stock, so the relevant cost will be 2,000 units × £14/unit = £28,000. Material B is in stock (1,200 units) but is regularly used in production; thus, its opportunity cost, which is the replacement cost, is relevant. So, the cost for Material B is 800 units (as 1,200 are in stock) × £12/unit = £9,600. For Material C, with 2,000 units needed and 1,400 in stock, the material cannot be used elsewhere, so the relevant cost is the realisable value, not the book value or replacement cost. Therefore, 600 units at £10/unit = £6,000, plus the realisable value of surplus stock (1,400 units × £5/unit = £7,000). Material D is a bit more complex since it can substitute another material, E, which costs £10/unit. We need 400 units of D, the realisable value of which exceeds the cost of material E; therefore, we should sell D at £12/unit and purchase E instead, leading to a relevant cost for D of 400 units × £10/unit = £4,000.
Adding these together, we calculate the total relevant cost as: £28,000 + £9,600 + £6,000 + £7,000 + £4,000 = £84,600. Since the revenue from the job is £88,000, the profit for undertaking the job would therefore be £88,000 - £84,600 = £3,400. Thus, it would be financially beneficial for Reilly Ltd to accept the job.