If the fourth floor is "off-line" with the central station due to welding and cutting, and during the course of the day, an initiating device is activated on the eleventh floor, what action should the Fire Life Safety Director take?

1 Answer

4 votes

Final answer:

When the central station is off-line and an initiating device is activated on another floor, the Fire Life Safety Director must act immediately to ensure safety, even if it requires manual intervention.

Step-by-step explanation:

If the fourth floor is "off-line" with the central station due to welding and cutting, and an initiating device is activated on the eleventh floor, the Fire Life Safety Director should immediately take action to ensure the safety of the building's occupants. This includes communicating with the emergency services, initiating fire alarm procedures, and executing the building's emergency action plan. Since the central station is not receiving signals from the fourth floor, the director must manually assess the situation there, ensuring that all personnel are safe and that proper evacuation procedures are followed on all affected floors.

User Amit Battan
by
8.3k points