64.2k views
3 votes
The earliest finish time for the final activity on a project network is also the total completion of the project.

a. True
b. False

User Jack Jin
by
8.3k points

1 Answer

2 votes

Final answer:

The given statement is false because the earliest finish time for the final activity on a project network is not necessarily the total completion of the project. It depends on the dependencies between activities and their durations (option b).

Step-by-step explanation:

The earliest finish time for the final activity on a project network is not necessarily the total completion of the project. It depends on the dependencies between activities and their durations.


Let's consider an example to understand this better:

  1. Activity A takes 3 days to complete.
  2. Activity B is dependent on Activity A and takes 2 days to complete.
  3. Activity C is dependent on Activity B and takes 4 days to complete.


In this network, the earliest finish time for the final activity (Activity C) is 9 days. However, the total completion time of the project would be 9 days + the earliest start time for Activity A. If Activity A can start on day 0, then the total completion time of the project would be 9 days. But if Activity A can only start on day 2, then the total completion time would be 11 days.


Therefore, the earliest finish time for the final activity on a project network is not necessarily the total completion of the project.

Hence, the answer is option b.

User Arjoonn
by
9.2k points

No related questions found