63.8k views
1 vote
The City issued a request for bids for the construction of an events centre; the terms stated that the closing would be June 30 at 4:00 p.m. of the current year. At 4:15 p.m. on June 30, a representative of Joe's Construction arrived at the City offices to submit a bid. There was discussion about the fact that the stated deadline had passed, but the person from Joe's Construction said that the submission was being made on June 30 while the City offices were still open, and the only reason there had been a delay was a problem locating the company managers who needed to sign the bid. Which of the following statements is true?

A) If Joe's Construction's bid is the most competitive bid, the City will be obligated to accept it and award the contact to Joe's Construction.
B) The City must still consider the bid from Joe's Construction as it is required to treat all parties equally and in good faith.
C) If Joe's Construction has worked for the City previously and this is the first time there has been a problem with a late submission, the City should consider the bid in good faith.
D) The bid from Joe's Construction cannot be considered, as it does not comply with the terms of the tender.
E) The City should confirm that there was a problem getting the signatures and, if so, consider the bid from Joe's Construction as having been submitted on time.

1 Answer

2 votes

Final answer:

The bid from Joe's Construction is ineligible for consideration because it was submitted past the deadline set by the City, regardless of previous working relationships or reasons for the delay.

Step-by-step explanation:

The question presented concerns the legal principles related to a tender process and the acceptance of bids. In the scenario described, Joe's Construction submitted a bid for the construction of an events centre after the closing deadline stipulated by the City. According to standard legal and contractual principles, the bid from Joe's Construction cannot be considered because it was not submitted in accordance with the terms set forth in the request for bids. The deadline was clearly stated as June 30 at 4:00 p.m., and the submission at 4:15 p.m. does not comply with these terms. Past working relationships and the reason for the bid's delay do not typically influence the enforceability of these terms. Therefore, letter D is the true statement: The bid from Joe's Construction cannot be considered, as it does not comply with the terms of the tender.

User JackMahoney
by
8.0k points