It is the Scrum Master's job to estimate story points.

A) True
B) False

User Paul Riker
by
8.0k points

1 Answer

6 votes

Final answer:

The claim that estimating story points is the job of the Scrum Master is false. Story points are estimated by the Development Team and the Scrum Master facilitates the process without providing the estimates themselves.

Step-by-step explanation:

The statement that it is the Scrum Master's job to estimate story points is false. In the Scrum framework, the Development Team is responsible for estimating the amount of work for a user story, typically in the form of story points. The role of the Scrum Master is to facilitate the Scrum events, coach the team in Scrum practices, and ensure that any obstacles to progress are removed, not to provide estimates for the work to be done. Estimation is a collaborative effort during the Sprint Planning meeting and involves all members of the Development Team; the Scrum Master may facilitate this process, but the team as a whole should come to a consensus about the effort required for each user story or backlog item.

User Anirban Paul
by
9.2k points