21.6k views
2 votes
A firm resides at the lowest level of all project management maturity models presented in the text:

a. If its project processes are merely repeatable
b. If its project management activities are directed by a specialized project office
c. If lessons learned form one project are capture and transferred to other project management teams
d. If its project management processes are ad hoc in nature

User Dwaddell
by
8.4k points

1 Answer

6 votes

Final answer:

The subject of this question is Business, and the lowest level in project management maturity models is defined. The correct answer is provided with an explanation of ad hoc project management processes.

Step-by-step explanation:

The subject of this question is Business and the grade level is College.

The question is related to project management maturity models and identifying the lowest level.

The correct answer is d. If its project management processes are ad hoc in nature.

At this level, project management processes are not standardized and follow a different path for every cycle.

For example, in a company where project management processes are ad hoc, there is no consistent approach to managing projects.

Each project may be handled differently, leading to inconsistencies and inefficiencies.

User Ivaylo Novakov
by
8.3k points