135k views
4 votes
For an activity in a cpm analysis, the early start time is 8 and the late start time is 10. which of the following statements is true?

a. the early finish is 10. the late finish is 12.
b. the activity is on the critical path.
c. the duration of this activity is 2.
d. the slack for this activity is 2.

1 Answer

5 votes

Final answer:

d. The slack for this activity is 2.

Step-by-step explanation:

The correct statement for the given activity in a CPM analysis is:

d. the slack for this activity is 2.

Slack is the amount of time an activity can be delayed without delaying the project. In this case, the difference between the late start time (10) and the early start time (8) is 2, which indicates that there is a slack of 2 hours for this activity.

User Will Gordon
by
7.8k points