Upon request of the owner, and prior to the expiration of _____, the architect shall, ______, conduct a meeting with the owner to review the facility operations and performance?

User Joniece
by
8.0k points

1 Answer

4 votes

Final answer:

The question pertains to a post-construction meeting between a property owner and an architect to review facility operations, which takes place within a specified warranty period outlined in their contract.

Step-by-step explanation:

The subject of the question is related to contractual obligations between a property owner and an architect, particularly in the context of a post-construction operational review meeting. The blank in the question should be filled with a specific time period that is contractually agreed upon between the two parties. Typically, this could be one year or another set term after project completion, known as the warranty period. The architect must, within this time frame and upon the owner's request, conduct a meeting to review how the facility operates and performs.

This type of clause is usually included in the contract documents to ensure that the architect provides support during the early stages of building occupation. It allows the owner to address any issues that may have arisen since taking possession of the facility. If this process is part of a formal agreement, it could also fall under a warranty review or similar post-occupancy evaluation.

From the provided reference information, it's clear that both possession terms and termination clauses have specific requirements, and the concept of written notice is a key element of such agreements, whether in a lease or professional services context.

User Nishant Bhardwaj
by
9.5k points