224k views
4 votes
33 - How much notice must be given to each utility owner having underground utilities in a proposed excavation site?

1 - Not less than 2 or more than 10 days prior to start of excavation
2 - Not less than 3 or more than 10 days prior to start of excavation
3 - Not less than 2 or more than 12 days prior to start of excavation
4 - Not less than 4 or more than 10 days prior to start of excavation

User Beachhouse
by
8.5k points

1 Answer

5 votes

Final answer:

The correct answer is option 1 - Not less than 2 or more than 10 days prior to start of excavation. Proper notice is important to ensure safety and prevent disruptions during excavation.

Step-by-step explanation:

The correct answer is option 1 - Not less than 2 or more than 10 days prior to start of excavation. This means that when planning an excavation, notice must be given to each utility owner at least 2 days in advance, but no more than 10 days in advance of the start of excavation.

Proper notice is important to ensure the safety of workers and prevent damage to underground utilities. The utility owners need time to mark the location of their utilities and take any necessary precautions.

Providing adequate notice helps prevent accidents and disruptions during the excavation process. It allows utility owners to plan and prepare accordingly, ensuring the safety of the workers and the integrity of the underground utilities.

User Surya Matadewa
by
8.5k points