174k views
4 votes
Nonfulfillment of a condition:

A will excuse a duty to perform that was subject to the condition

B gives rise to liability for nonperformance

C does not excuse the other party's duty to perform under the contract

D will result in a breach of contract

1 Answer

4 votes

Final answer:

Nonfulfillment of a condition will excuse a duty to perform but will result in a breach of contract by the non-performing party.

Step-by-step explanation:

Nonfulfillment of a condition will excuse a duty to perform that was subject to the condition, but will not excuse the other party's duty to perform under the contract. Instead, it will result in a breach of contract by the non-performing party. For example, if Party A agreed to sell their car to Party B on the condition that Party B pays the full amount within 30 days, but Party B fails to make the payment, then Party B would be in nonfulfillment of the condition and Party A would have a right to consider the contract breached.

User Tot
by
8.2k points