Final answer:
The processes integrated and coordinated during the Control Procurements process are Plan Procurements, Monitor Communications, Control Quality, and Perform Integrated Change Control (option C).
Step-by-step explanation:
The question pertains to the Control Procurements process of project management, which is about managing procurement relationships, monitoring contract performance, and making changes and corrections as needed. During the Control Procurements process, several other processes must be integrated and coordinated.
Among the options given, option C is correct which includes: Plan Procurements, Monitor Communications, Control Quality, and Perform Integrated Change Control. These areas are critical to ensuring that procurement activities align with the project plan, that there is clear and effective communication regarding procurements, that the deliverables meet the quality requirements, and that any necessary changes are managed in an integrated manner.