Tim has requested to install a security update to the Dion Training web server during the next maintenance window. At the change control board meeting, Tim presents the requested change and gains approval from the change board. Before Tim installs the update, which of the following should be documented as a result of the change board's approval?

a. Risk level of the change
b. Purpose of the change
c. Affected systems/impact of the change
d. Date and time of the change

1 Answer

4 votes

Final answer:

option d,In response to Tim's installation of a security update on the web server, the change control board's approval must be documented including the risk level, purpose, affected systems/impact, and date/time of the change.

Step-by-step explanation:

Once the change control board approves Tim's request to install a security update to the Dion Training web server, several pieces of information need to be properly documented. These include:

  • Risk level of the change
  • The purpose of the change
  • Affected systems/impact of the change
  • Date and time of the change

Proper documentation ensures that the team is aware of the ramifications of the update and can plan accordingly. It is also essential for tracking changes and managing the IT infrastructure effectively.