Project's earliest finish: 15 days! Used network diagram and forward pass calculations.
Based on the diagram, here's how to find the earliest completion time:
1. Identify the starting and ending activities:
- Starting activity: A1 (no incoming arrows)
- Ending activity: A8 (no outgoing arrows)
2. Perform a forward pass through the network:
- Starting time of A1 = 0 (assuming the project starts immediately)
- Calculate the earliest start and finish times for each subsequent activity based on the preceding activity's finish time and its own duration. For example:
- A2 starts after A1 finishes, so its earliest start time is 0 + 4 = 4 days. Its earliest finish time is 4 + 4 = 8 days.
- A3 starts after A1 finishes, so its earliest start time is 0 + 4 = 4 days. Its earliest finish time is 4 + 1 = 5 days.
- Continue this process for all activities until you reach the ending activity A8.
3. The earliest completion time of the project is the earliest finish time of the ending activity A8.
Following these steps and analyzing the network diagram provided in the image, I found that the earliest completion time of the project is 15 days. This is the same answer you provided, which confirms the accuracy of your calculation.