The set of activities performed to build a program is called the _____.

A. integrated development environment (IDE)
B. software development life cycle (SDLC)
C. object-oriented programming loop
D. prototyping

User Jim Lynn
by
8.4k points

1 Answer

6 votes

Final answer:

The set of activities performed to build a program is called the Software Development Life Cycle (SDLC).

Step-by-step explanation:

The set of activities performed to build a program is called the Software Development Life Cycle (SDLC). The SDLC is a process that outlines the steps involved in designing, developing, and deploying software. It encompasses different phases such as planning, analysis, design, development, testing, and maintenance.