87.4k views
1 vote
A cost that is incurred because of a long-range policy decision is known as a:

A. discretionary cost.
B. committed cost.
C. continuous cost.
D. standard cost.

User Vida
by
8.4k points

1 Answer

7 votes

Final answer:

A cost that is incurred because of a long-range policy decision is known as a committed cost. Committed costs are expenses that a business is obligated to pay as a result of previous decisions or agreements.

Step-by-step explanation:

A cost that is incurred because of a long-range policy decision is known as a committed cost. Committed costs are expenses that a business is obligated to pay as a result of previous decisions or agreements, such as fixed costs or contracts. For example, if a company decides to build a new manufacturing plant, the expenses associated with the construction and operation of the plant would be considered committed costs.

User Stan Luo
by
8.3k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.